Fourth Unit of Rumaila Combined Cycle Power Plant Receives PAC
تاریخ خبر : 18 اردیبهشت 98

نخستین توربین کلاس F گروه مپنا به نیروگاه اندیمشک بارگیری شد

MAPNA Construction and Development of Combined Cycle Power Plants Company (MD-2) received a provisional acceptance certificate (PAC) for Unit 4 in Phase 1 of Rumaila Combined Cycle Power Plant project on Tuesday, February 5th, 2019.
With provisional delivery of this unit, MD-2 has now received PAC for 88 units, with an aggregate capacity of 13,411 MWs.
Rumaila Combined Cycle Power Plant
Design, procurement, transportation, installation, commissioning, and supervision of civil construction works was carried out by MAPNA Group. Shamara Holding, client of the project, carried out civil construction operations.
Phase 1 of the Rumaila Power Plant project includes construction of six gas-fired units which run on MAPNA Group's indigenous MAP2B turbines.
The initial efficiency of Phase I simple cycles stands at 34.6 percent. The figure will reach 36 percent one year after the provisional delivery.
Phase 2 of the project includes construction of three E-type steam cycles, HRSGs (without supplementary firing), ACC cooling system, and BOP (balance of plant).
Phase 3 of the Rumaila Power Plant project also includes construction of six gas-fired units running on MAPNA Group's MAP2B turbines.
The initial efficiency of Phase 3 simple cycles stands at 34.6 percent. The figure will reach 36 percent one year after the provisional delivery.
Phase 4 of the project includes construction of three E-type steam cycles, HRSGs (without supplementary firing), ACC cooling system, and BOP (balance of plant).
Upon completion, the plant will include six 500-MW combined cycle power blocks in Rumaila, in vicinity of Basra, Iraq's second largest city.
Shamara Holding is the client of the project and MAPNA Combined Cycle Power Plants Construction and Development (MD-2) serves as the contractor.