MAPNA Group receives provisional acceptance certificate (PAC) for the steam cycle of Yazd Taban Combined Cycle Power Plant.
MAPNA Combined Cycle Power Plants Construction & Development (MD-2) Company, the executor of the project, received the certificate on April 6th, 2019.
With provisional delivery of the unit, MD-2 has now received PAC for 89 units with an aggregate capacity of 13,571 MWs.
About Yazd Taban Project
Yazd Taban Project was commissioned to MD-2 on April 20th, 2012.
Located southeast of the city of Yazd in central Iran, the power plant comprises of two gas-fired units each with a capacity of 162 MWs, one steam unit with a capacity of 160 MWs; a Heller cooling tower, and a 400-kv power transmission line.
The client of this project is Jam Energy Development Company and the consultant of the project is Ghods Niroo Consulting Engineers Company.